Customer: Weydman Electric
End-User: Mohawk Valley Health Services
Duration: 2 years
SMART Electrical Solutions
CNC provided and installed a state-of-the-art communications network in the new Wynn Hospital. Our extensive experience in large facility build-outs provided leverage for the construction of the new hospital.
Services Provided:
Full communications network provided and installed.
• Provide & Install: 10,500 Cat6/6A cables 9 floors
• Buildout: 38 TelCom Rooms (TRs), 48-strand SM redundant fiber optic network
between 2 main TRs and 36 TRs on 9 floors.
• Termination & Testing of all copper and fiber cables
• Test Results, As-Builts, Shop Drawings, Documentation per specification
• Manufacturer warranty upon completion